Capsule house and main contractor: the interface matrix for foundations, cranage, services, tolerances, revision control, commissioning and site damage.

Crawler crane lowering a pod module onto foundation plinths while a site engineer signals

A factory-built capsule unit and a conventional site contractor meet at a small number of points, and almost every dispute on a mixed project happens at one of them. Foundations that do not match the anchor layout, a crane that cannot reach, services brought to the wrong place, a unit damaged after it was signed for, and nobody willing to own the snag list. This page sets out the interface as a matrix: who does what at each point, which documents have to move between the two parties and when, how revisions are controlled, and how to put a responsibility table into the contract. Briefing a local contractor on the work itself is a separate subject and stays in briefing a local contractor for a capsule home. Installation cost lines are in capsule house installation cost, foundation and ground work is in foundation and site preparation, and the commercial reference is capsule house price.

The interface matrix

Write this down before the foundation is poured, not after. Each row needs one named owner per party, and the empty rows are the problem.

InterfaceFactory scopeMain contractor scope
FoundationsLoad and anchor data, setting-out drawingDesign for local ground, build to tolerance, survey
Cranage and liftWeight, lift points, centre of gravityCrane, ground preparation, lift plan, permits
Service connectionsTermination points and internal servicesStubs brought to the defined point, earthing, testing
Weather protectionUnit sealed for transport, packingProtection after unpack until envelope closed
CommissioningAttendance scope and test procedureAccess, temporary power and water, labour
SnaggingRectification of defects in supplied scopeRectification of site works, access for others
Damage on siteDamage present at handover of the unitDamage after acceptance, and care of others' work

Foundations: the document that must move first

The foundation cannot be designed from a brochure. The contractor needs, before the pour:

  • A setting-out drawing showing anchor positions, hold-down layout and the tolerance each has to be held to.
  • Load data: the loads the unit imposes, and where they land.
  • Service entry positions so ducts and sleeves are cast in the right place rather than cut afterwards.
  • Access dimension confirmation, so the foundation is not built where the crane cannot reach.

The converse is also true: the factory cannot finalise the unit until it knows the foundation type and the local ground conditions. That exchange is the critical path item on most mixed projects, and it is the one most often left to run informally.

Workers in a site office standing before a wall drawing marking interface points between trades with coloured tape
A marked-up interface drawing on the site office wall resolves in ten minutes what email resolves in ten days.

Tolerances and survey obligations

Two tolerance regimes meet at the foundation, and they are usually specified by different people to different standards. The practical requirements are:

  • State the tolerance the unit can accommodate, in numbers, on the drawing.
  • State who surveys before the lift, and what happens if the tolerance is exceeded — shimming, rework, or rejection.
  • Record the as-built survey and hand it to both parties before the crane arrives.
  • Agree what "level" refers to: a datum, a single corner, or the mean of several points.

A foundation that is out of tolerance is rarely a disaster and always a delay. The delay is absorbed by whoever has the crane booked, which is why the survey clause is worth writing.

Cranage, access and the lift plan

The lift is a shared operation with a single moment of risk. Before the day:

  • Ground bearing confirmed for the crane on outriggers, including after rain.
  • Working radius checked against the actual placement position, not the nearest convenient one.
  • Overhead obstruction checked: trees, power lines, other buildings.
  • Lift plan and permits prepared by the party that owns the crane, with the factory's lift-point data incorporated.
  • Exclusion zone agreed and enforced, and the site programme arranged so other trades are not underneath.
  • Weather contingency: a stated wind threshold and a decision-maker, agreed in advance rather than argued on the day.

Service stubs: define the point, do not describe it

"Electrical connection" is not a scope; it is a category. Name the physical point at which one party's work ends and the other's begins, put it on a drawing, and say what each side supplies up to it. The two recurring failures are a stub installed on the wrong side of the unit and an isolator that both parties assumed the other would provide.

Drawing revision control

In a mixed project there are usually three drawing sets in circulation: the factory's, the contractor's and the designer's. Revision control is not bureaucracy here, it is the mechanism that prevents a foundation being built to a superseded layout. Agree:

  • One named contact on each side who is authorised to issue and accept revisions.
  • A revision numbering format and a dated register.
  • That site work proceeds only on the current issued revision, and that superseded sets are marked or withdrawn.
  • That any change affecting the interface triggers a written confirmation before work continues.
Surveyor with a tripod setting out anchor bolt positions on a cured concrete plinth before a unit arrives
Setting out against the current issued revision is the least costly insurance on the project.

Requests for information

An RFI is justified when the information is genuinely missing, not when it is inconvenient to find. Used well, it protects the programme by forcing a written answer with a date. Used badly, it becomes a paper trail of questions that could have been resolved by a phone call. The test worth applying: does the answer change what someone builds, and is the person asking unable to determine it from the documents issued?

Commissioning, snagging and damage

Three ownership questions need answering in writing before handover:

  • Commissioning. Who attends, who provides temporary services and labour, and what the test record looks like.
  • Snagging. Who compiles the list, who decides whether an item belongs to the factory or the site, and what the rectification period is.
  • Damage. At what moment does responsibility for the unit pass, and what record is taken at that moment. A dated photo set at handover resolves most arguments cheaply.

Attach the table to the contract

The output of this exercise is one page: the interface matrix, with a named owner per row, plus the document release dates and the revision control rule. Attach it to both contracts so that the factory and the contractor are looking at the same allocation. Where a clause has commercial consequences, have it reviewed by your own adviser rather than reused from another project. Requirements may vary by application, market and applicable standard.

Handover between the two scopes, recorded once

The matrix works only if the moment of transfer is recorded. Agree a single handover record covering the condition of the unit at arrival, the as-built foundation survey, the service stub positions as built, and the revision numbers of the drawings in force at that moment. One page, signed by both parties, taken before the crane leaves. It converts the three questions that cause most disputes — when did responsibility pass, what was already damaged, and which revision was built — into entries in a document rather than recollections.

One sentence that prevents most of it

If the project has time for only one clause, make it this: no work that another party's work depends on starts until the drawing revision it depends on has been issued in writing and accepted by both sides. Most interface failures are not technical. They are two competent teams building to two different versions of the same plan, and a single written acceptance step removes the category almost entirely.